- Project Name: Brew Water Tank Project
- Customer: PATHUMTANI BREWERY CO., LTD.
- Description: WCE’s SFS unit undertook the Brew Water Tank project, providing a comprehensive one-stop service. The scope of work included sourcing materials, welding and assembling the tank structure with all necessary equipment, transporting the tank to the site, and completing the installation. Quality checks were performed on the welds using both Visual Testing (VT) and Penetrant Testing (PT) methods. After installation, the tank was thoroughly cleaned. The entire project was completed within approximately 5 months.