• Project Name: Rotor Overhaul with CMM Measurement: Principles and a WCE MTE Case Study
  • Client: A pulp and paper manufacturer in Thailand
  • Description: Rotor overhaul: dismantled, CMM-measured, new spacers made, reassembled and adjusted, 100% complete on plan in 6 days

Summary

A rotor is the main rotating part of many industrial machines. Over time, its components wear and the assembly clearances drift. For this reason, a rotor overhaul means dismantling the rotor, measuring it precisely, making replacement parts, and then reassembling and adjusting it. This article explains the principles of a rotor overhaul, the role of a CMM, and why accurate spare parts matter. Finally, it presents a case study by WCE’s MTE business unit.

1. Why Does a Rotor Need an Overhaul?

A rotor runs under high loads and speeds all the time. Parts such as spacers, which set the distances between components on the shaft, slowly wear or deform. When clearances drift, the rotor may run out of balance and vibrate. As a result, its bearings may fail sooner. Therefore, a planned overhaul restores the rotor to its design condition.

2. Key Principles of a Rotor Overhaul

2.1 Measuring with a CMM

A coordinate measuring machine (CMM) uses a touch probe to measure the distances between points on a part in three dimensions. The most accurate machines reach nanometre-level sensitivity. Makers of ultra-precision parts, such as aircraft engine bearings, rely on this kind of measurement [1]. Measuring dismantled parts on a CMM therefore reveals their true size and wear.

2.2 Making Parts to Size

Measurement data then guides the making of new parts such as spacers. ISO 2768 sets general tolerances for linear and angular dimensions and for geometrical features of machined parts [3]. In addition, parts made within tolerance fit closely and hold components in the right place.

2.3 Rotor Balance

ISO 21940-11 sets procedures and tolerances for balancing rigid rotors. It covers permissible residual unbalance and the number of correction planes [2]. For this reason, correct assembly clearances form the basis for a well-balanced rotor.

2.4 Reassembly and Adjustment

Once the new parts are ready, the team reassembles the rotor in sequence. Next, it adjusts the clearances to the drawing. Finally, it checks the result with the machine owner before handover.

3. Case Study: Rotor Overhaul by WCE MTE

  • Scope: Rotor overhaul with part replacement, new spare parts, and rotor adjustment
  • Client: A pulp and paper manufacturer in Thailand
  • Duration: 12–17 October 2026 (6 days)
  • Progress: 100% complete, on plan

First, the MTE team dismantled the rotor and measured the parts with a CMM. Next, it made new spacers. Then the team reassembled and adjusted the rotor. Finally, it checked the work together with the client. As a result, the project finished on plan in 6 days.

The cover image is a concept illustration. In the background, a perspective line drawing shows a large rotor disc in the workshop. On the right, a front view of the rotor and a section of the shaft assembly highlight the new spacers and the CMM probe in red. The four work steps complete the drawing. All images were created with AI assistance, so no person or client can be identified.

4. Lessons from This Project

A rotor overhaul that must finish within days needs both precise measurement and in-house parts making. In addition, having a CMM and machine tools in one team means accurate parts can be made and delivered on time.

5. WCE Services

WCE’s MTE (Machinery Technology and Engineering) business unit manufactures, repairs, and overhauls large machinery parts, including dimensional inspection and replacement parts.

Contact: +66 65-937-6283 | international@wce.co.th | www.wce.co.th
We engineer your success.

References

  1. National Institute of Standards and Technology. (2017). Introducing Xenos, NIST’s Largest Coordinate Measuring Machine. https://www.nist.gov/node/1186411 (accessed 20 November 2026)
  2. ISO. (2016). ISO 21940-11:2016 Mechanical vibration – Rotor balancing – Part 11: Procedures and tolerances for rotors with rigid behaviour. https://www.boutique.afnor.org/en-gb/standard/iso-21940112016/mechanical-vibration-rotor-balancing-part-11-procedures-and-tolerances-for-/xs026522/125630 (accessed 20 November 2026)
  3. Rees, J. (2018). ISO 2768 – A Basic, Simplified Guide. Mechanical-Engineering.com. https://mechanical-engineering.com/iso-2768-2/ (accessed 20 November 2026)

✉️

Purchasing Department : phaiboono@wce.co.th   |   Human Resources and Administration Department : hrmwce@wce.co.th   |   Sales Department : international@wce.co.th

Headquarters Bangkok

16 K&Y Building 5 Fl., Surasak Road, Silom Sub-District, Bangrak District, Bangkok, 10500

Sales Department: +66 (0) 6 5937 6283
Accounting (Bangkok): +66 (0) 81 986 7190
Procurement Department: +66 (0) 81 941 0128
Careers & Internships: +66 (0) 64 934 2684
Fax: +66 (0) 2233 6669

Factory Bang Saphan

9/1 Moo 4, BanKlangNa–YaiPloy Road, Maerumphueng, BangSaphan, PrachuapKhiriKhan 77140

Telephone +66 (0) 3290 6112 – 119
Sales Department: +66 (0) 6 5937 6283
Accounting (Factory): +66 (0) 81 149 0614
Procurement Department: +66 (0) 81 941 0128
Careers & Internships: +66 (0) 64 934 2684
Fax +66 (0) 3290 6120